Mounting the solenoid valve

In order to mount the solenoid valves for the CRII capacity control as described below, it is required that the respective CRII cylinder heads are pre-mounted on the compressor.

In order to mount the solenoid valves for the CRII capacity control as described below, it is required that the respective CRII cylinder heads are pre-mounted on the compressor.

Step 1: Remove blind flange from CRII cylinder head

Step 2: Clean sealing face

Step 3: Position new gasket and spring

Step 4: Mount solenoid valve and cable bracket with new screws

Attach the cable bracket only to the cyclinder head side shown in the video.

Attach the cable bracket only to the cyclinder head side shown in the video.

Step 5: Place gasket on electric connector of the device

Step 6: Screw electric connector of the device to solenoid coil

Risk of compressor damage!

Risk of compressor damage!

Only use suitable original solenoid coils!

Step 7: Place solenoid coil onto armature and tighten with nut and washer

Step 8: Connect cable cores to terminal strip CN6 of the compressor module

  1. Shorten cables as required and guide them through screwed cable glands at compressor module into CM-RC housing.
  2. Connect cable cores to terminal strip CN6. See also chapter Schematic wiring diagrams.